This project would replace a failing sewage system at the North Shore Lodge. A new drain field would be installed outside the current permit area. The permit would be amended to reflect this additional area. Work would meet CDHD requirement.
Location
North Shore Lodge at Warm Lake
Project timeline
1
Scoping Start
06/01/2010
2
Decision
06/2010 (Estimated)
3
Implementation
07/2010 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| North Shore Lodge Septic System Replacement Project | Decision Signed Date: 06/17/2010 Legal Notice Date: 06/17/2010 |
| Forests | Boise National Forest |
| Districts | Cascade Ranger District |
| Legal Land Description | T. 15 N., R. 6 E., Section 12; Boise Meridian, Valley County, Idaho. |