This project proposes to conduct about 1,200 acres of thinning, hand piling, and pile burning over a 5-year period.
Location
Shafer Creek, Sinker Creek, and Bogus Creek drainages
Project timeline
1
Scoping Start
05/04/2011
2
Decision
06/2011 (Estimated)
3
Implementation
09/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Boise Ridge Timber Stand Improvement Project | Decision Signed Date: 06/20/2011 |
| Forests | Boise National Forest |
| Districts | Mountain Home Ranger District |