Reintroduce low to moderate intensity fire to restore desired vegetative conditions and reduce natural fuel loads and ladder fuels on 360 acres.
Location
Horsethief Creek
Project timeline
1
Scoping Start
12/22/2011
2
Decision
02/2012 (Estimated)
3
Implementation
09/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | National Fire Plan - Healthy Forests Initiative Alternative Consultation Arrangements |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Horsethief Project | Decision Signed Date: 02/16/2012 |
| Forests | Boise National Forest |
| Districts | Cascade Ranger District |
| Legal Land Description | T.14N., R5E., sections 20 and 21 |