The purpose of this project is to restore vegetation conditions on about 1,626 acres of ponderosa pine plantations on the Emmett Ranger District. Plantations would be thinned using chainsaws followed by activity fuels treatments.
Location
The project area is located in the Pyle Creek and Anderson Creek subwatersheds.
Project timeline
1
Scoping Start
06/20/2012
2
Decision
04/2014 (Estimated)
3
Implementation
07/2014 (Estimated)
NEPA / regulatory detail
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Forest Vegetation Improvements |
| Forests | Boise National Forest |
| Districts | Emmett Ranger District |
| Legal Land Description | T10N, R05E, Sections 31 & 32 and T09N, R05E, Sections 04-09, 15-18, 20, and 21 |