This project proposes hazardous fuel reduction on approximately 9,400 acres within the Wildland Urban Interface (WUI). Proposed treatments include both prescribed fire and mechanical understory thinning.
Location
The project is located adjacent to the community of Lowman along the South Fork of the Payette River.
Project timeline
1
Scoping Start
02/12/2020
2
Comment Period
02/12/2020
3
Objection Period Start
06/17/2020
4
Decision
08/2020 (Estimated)
5
Implementation
10/2020 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Lowman Wildland Urban Interface (WUI) Project | Decision Signed Date: 08/10/2020 |
| Forests | Boise National Forest |
| Districts | Lowman Ranger District |
| Legal Land Description | Not Applicable |