Decision Memo Completed

South Fork Fish Weir SUP Project

Boise National Forest Valley, Idaho Cascade Ranger District

Authorize the US Fish and Wildlife Service to construct an additional pond in a disturbed area within the existing permit boundary at the South Fork Salmon River Fish Weir. Decision Memo issued on June 3, 2015.

Location

SW1/4, NW1/4 of Section 2, T15N, R6E, Boise Meridian along the South Fork of the Salmon River near Warm Lake.

Project timeline

1
Scoping Start
03/13/2015
2
Decision
06/2015 (Estimated)
3
Implementation
06/2015 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction; Special Use Authorizations
2015 South Fork Fish Weir Special Use Permit Holding Pond ConstructionDecision Signed Date: 06/03/2015
ForestsBoise National Forest
DistrictsCascade Ranger District
Legal Land DescriptionNot Applicable
Special use management