Decision Memo Completed

Century Link Fiber Optic Cable Project 2018

Boise National Forest Boise, Idaho Idaho City Ranger District

CenturyLink proposes to add 20 miles of fiber optic cable, approximately 6.0 miles of which crosses National Forest System (NFS)lands; new cable on NFS lands will be installed in/along existing roads in Grimes Greek, Idaho City and Centerville areas.

Location

NFS roads in the Grimes Creek, Idaho City and Centerville areas

Project timeline

1
Scoping Start
05/24/2018
2
Decision
06/2018 (Estimated)
3
Implementation
07/2018 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Century Link Fiber Optic Cable Project 2018 DMDecision Signed Date: 06/27/2018
ForestsBoise National Forest
DistrictsIdaho City Ranger District
Legal Land DescriptionNot Applicable
Special use management