The Forest Supervisor has signed a Decision Memo authorizing BSU, in partnership with the NRCS, to install a weather station at Lower Deer Point.
Location
Lower Deer Point
Project timeline
1
Scoping Start
11/28/2018
2
Decision
06/2019 (Estimated)
3
Implementation
07/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Research And Development |
| BSU Dry Creek Experimental Watershed Weather Station Decision Memo | Decision Signed Date: 06/26/2019 |
| Forests | Boise National Forest |
| Districts | Mountain Home Ranger District |
| Legal Land Description | Section 29, T.5.N., R.3.E Boise Meridian |