The Boise National Forest would authorize Idaho Power Company to reroute approximately 2.49 miles of existing overhead 7.2-kilovolt (kV) distribution line with approximately 2.74 miles of single-phase underground line.
Location
Yellow Pine area.
Project timeline
1
Scoping Start
01/13/2020
2
Decision
02/2020 (Estimated)
3
Implementation
05/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (2), 36 Cfr 220.6(E)(2) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Idaho Power-Warm Lake Distribution Line Relocation (WMLK-11) | Decision Signed Date: 02/12/2020 |
| Forests | Boise National Forest |
| Districts | Cascade Ranger District |
| Legal Land Description | Township 18 North, Range 08 East, Section 04, and Township 19 North, Range 08 East, Sections 28, 29, 32, & 33, Boise Meridian. |