Idaho Power Schoolhouse / Dixie Line Project

Boise National Forest Elmore, Idaho Mountain Home Ranger District

Idaho Power Company (IPC) proposes to rebuild and reroute approximately 1,990 feet of the existing overhead powerline line with approximately 2,150 feet of overhead line along the westerly right-of-way (ROW) of Lester Creek Road, south of Pine, ID.

Location

Section 30, T2N, R10E, Boise Meridian

Project timeline

1
Scoping Start
04/25/2019
2
Decision
03/2020 (Estimated)
3
Implementation
04/2020 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityElectric Transmission; Facility Improvements/Construction; Special Use Authorizations; Facility Maintenance
Idaho Power Schoolhouse / Dixie Line ProjectDecision Signed Date: 03/20/2020
ForestsBoise National Forest
DistrictsMountain Home Ranger District
Legal Land DescriptionNot Applicable