Decision Memo Completed

Burntlog Route Geophysical Investigation

Boise National Forest Valley, Idaho Cascade Ranger District

The purpose of the investigation is to collect crucial geophysical data along the existing Burntlog road and proposed new alignment between Trapper Creek and Stibnite.

Location

Burntlog road

Project timeline

1
Scoping Start
02/10/2020
2
Decision
03/2024 (Estimated)
3
Implementation
06/2024 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (8), 36 Cfr 220.6(E)(8)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityMinerals Or Geology Plans Of Operations
Burntlog Route Geophysical Investigation CE review and Decision MemoDecision Signed Date: 03/01/2024 (FS Withdrawn)
ForestsBoise National Forest
DistrictsCascade Ranger District
Legal Land DescriptionThe project is located in sec 12, T15N, R7E; sec 3, 4, 7, 9, 17, 18, T15N, R8E; sec 1, 2, 10, 11, 15, 22, 26, 27, 34, 35, T16N, R8E; sec 13, 23, 24, 26, 35, 36, T17N. R8E; sec 4, 5, 8, 17, 18, T17N. R9E; sec 13, 14, 24-26, 32-34 T18., R9E, Boise Meridian
Minerals and geology