Bureau of Reclamation has completed a Draft EIS for the Boise River Basin Feasibility Study. The USFS is a cooperating agency. To accomplish this project the USFS would need to modify a Forest Roads and Trails Act Easement.
Location
Anderson Ranch Reservoir, 28 miles northeast of Mountain Home, Idaho.
Project timeline
1
NOI in Federal Register
08/09/2019
2
DEIS NOA in Federal Register
07/31/2020
3
FEIS NOA in Federal Register
10/2024 (Estimated)
4
Objection Period Start
04/2024 (Estimated)
5
Decision
12/2024 (Estimated)
6
Implementation
06/2025 (Estimated)
NEPA / regulatory detail
| Special Authority | Nepa Document Prepared By Another Federal Agency |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Facility Improvements/Construction; Road Improvements/Construction |
| Forests | Boise National Forest |
| Districts | Mountain Home Ranger District |
| Legal Land Description | Not Applicable |