This project proposes to fully replace the existing timber bridge located on National Forest System Road 693.
Location
Scriver Creek Road, milepost 3.9
Project timeline
1
Scoping Start
12/09/2020
2
Decision
04/2021 (Estimated)
3
Implementation
05/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance |
| Decision Decided Date | 04/07/2021 |
| Forests | Boise National Forest |
| Districts | Emmett Ranger District |
| Legal Land Description | Section 17 of Township 10 North, Range 4 East |