Decision Memo Completed

Two Bit Creek Culvert Replacement

Boise National Forest Valley, Idaho Cascade Ranger District

The project proposes to replace the existing barrier culvert on Two Bit Creek with Aquatic Organism Passage (AOP) structures which will re-establish unimpeded fish passage to all age classes of anadromous and resident fish species.

Location

Two Bit Creek at National Forest System road 493

Project timeline

1
Scoping Start
08/23/2021
2
Decision
12/2021 (Estimated)
3
Implementation
06/2022 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (18), 36 Cfr 220.6(E)(18)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityWatershed Improvements
Two Bit Creek Culvert ReplacementDecision Signed Date: 12/17/2021
ForestsBoise National Forest
DistrictsCascade Ranger District
Legal Land DescriptionSection 3 of Township 15 North, Range 6 East
Watershed managementWildlife, fish, rare plants