The project proposes to replace the existing barrier culvert on Two Bit Creek with Aquatic Organism Passage (AOP) structures which will re-establish unimpeded fish passage to all age classes of anadromous and resident fish species.
Location
Two Bit Creek at National Forest System road 493
Project timeline
1
Scoping Start
08/23/2021
2
Decision
12/2021 (Estimated)
3
Implementation
06/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Two Bit Creek Culvert Replacement | Decision Signed Date: 12/17/2021 |
| Forests | Boise National Forest |
| Districts | Cascade Ranger District |
| Legal Land Description | Section 3 of Township 15 North, Range 6 East |