There is a need to provide a cost-effective material source to facilitate road maintenance in the Bear Valley area. The proposal is to re-open and expand the existing borrow source located adjacent to Forest Road 579.
Location
The project is located 3/8 mile southwest of the intersection of Forest Road 582 and Forest Road 579.
Project timeline
1
Scoping Start
04/14/2021
2
Comment Period
04/14/2021
3
Objection Period Start
08/04/2021
4
Decision
12/2021 (Estimated)
5
Implementation
05/2022 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Maintenance |
| Bear Valley Borrow Source Development | Decision Signed Date: 12/07/2021 |
| Forests | Boise National Forest |
| Districts | Lowman Ranger District |
| Legal Land Description | Section 2 Township 12 North, Range 9 East. |