The purpose of the project is to protect people, homes, and improve the safety of evacuation routes within the project area in the event of wildfire. Reduce the frequency, extent, severity, and intensity of uncharacteristic or undesirable wildfire.
Location
Highway 21 along the Upper South Fork Payette River.
Project timeline
1
Scoping Start
10/05/2022
2
Comment Period
10/05/2022
3
Objection Period Start
07/12/2023
4
Decision
09/2023 (Estimated)
5
Implementation
10/2023 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels) |
| Upper South Fork Payette River Community Protection Project | Decision Signed Date: 09/25/2023 |
| Forests | Boise National Forest |
| Districts | Lowman Ranger District |
| Legal Land Description | Not Applicable |