Approval of a Plan of Operations (PoO) for the Calumet Placer Mine(placer operation) and Bear Track Mine(hardrock underground mine). The 4.8 acre mine would be placer mined over a 5 year period and a collapsed/bridged shaft would be reopened.
Location
Approximately 3 miles south of Warren ID
Project timeline
1
Scoping Start
02/14/2010
2
Comment Period
02/14/2010
3
Decision
06/2010 (Estimated)
4
Implementation
08/2010 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Calumet Placer & Bear Track Lode Mines DN / FONSI | Decision Signed Date: 06/04/2010 Legal Notice Date: 06/10/2010 |
| Forests | Payette National Forest |
| Districts | McCall Ranger District |
| Legal Land Description | T22N R6E Boise Meridian |