The proposed action would install three vault toilets and bury approximately 1,400 feet of communication cable.
Location
Brundage Mountain Resort
Project timeline
1
Scoping Start
04/07/2011
2
Decision
10/2011 (Estimated)
3
Implementation
11/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Brundage Mountain Toilet and Communication Project | Decision Signed Date: 10/06/2011 |
| Forests | Payette National Forest |
| Districts | McCall Ranger District |
| Legal Land Description | T. 19 N., R. 2 E., Section 12; T. 19 N., R. 3 E., Section 7; Boise Meridian, Adams County, Idaho |