Decision Memo Completed

Surdam Multiple Use Trail Construction

Payette National Forest Washington, Idaho Council Ranger District

Trails 275 and 275A would be connected to form a loop. This would accommodate ATVs, motorcycles and non-motorized users. 3.4 miles of trail would be constructed, 1.1 miles of trail is an existing trail bed, 2.3 miles would be new construction.

Location

10 miles west of Cambridge, Idaho

Project timeline

1
Scoping Start
08/30/2011
2
Decision
10/2011 (Estimated)
3
Implementation
06/2012 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (1), 36 Cfr 220.6(E)(1)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityTrail Management
CE ChecklistDecision Signed Date: 10/30/2011
ForestsPayette National Forest
DistrictsWeiser Ranger District
Legal Land DescriptionT15N R4 W Sections 30 & 31 and T15N R5W Sections 25, 26, 35, & 36
Recreation management