Project timeline

1
Scoping Start
03/01/2013
2
Comment Period
03/01/2013
3
Decision
09/2013 (Estimated)
4
Implementation
09/2013 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Outfitter and Guide Permit IssuanceDecision Signed Date: 09/18/2013
ForestsPayette National Forest
DistrictsKrassel Ranger District
Legal Land DescriptionNot Applicable