The proposed action would re-route eight sections of the Jackson Creek (#116) Trail. Old sections of trail would be decommissioned.
Location
The project area is located in the Upper French Creek drainage approximately 20 air miles North of McCall, Idaho
Project timeline
1
Scoping Start
02/06/2014
2
Decision
11/2014 (Estimated)
3
Implementation
07/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Jackson Creek Trail (#116) Reroute | Decision Signed Date: 11/25/2014 |
| Forests | Payette National Forest |
| Districts | McCall Ranger District |
| Legal Land Description | Township 21 North, Range 4 East, Section 6, Township 22 North Range 4 East, Sections 19, 30, and 31, and Township 22 North Range 3 East, Sections 13 and 24 in Valley and Idaho Counties, Idaho |