Decision Memo Completed

Sugar Creek Storm Treatment and Ford Rehabilitation

Payette National Forest Valley, Idaho Krassel Ranger District

This project would implement storm damage risk reduction road restoration treatments on approximately 4.5 miles of FS Road 51883 and restore the road ford crossing at Sugar Creek for the protection of endangered fish habitat in the adjacent stream.

Location

This project is located approximately 7 air miles E of Yellowpine, Idaho within the Sugar Creek watershed, a tributary to the East Fork South Fork Salmon River.

Project timeline

1
Scoping Start
04/01/2016
2
Decision
07/2016 (Estimated)
3
Implementation
07/2016 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (18), 36 Cfr 220.6(E)(18)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance
Sugar Creek Storm Treatment and Ford RehabilitationDecision Signed Date: 07/14/2016
ForestsPayette National Forest
DistrictsKrassel Ranger District
Legal Land DescriptionNot Applicable
Watershed managementRoad management