This project will address both restoration and public & private access needs to determine the minimum road system, improve watershed condition, provide ATV and motorcycle trail opportunities, and provide dispersed camping and parking opportunities.
Location
The project area is the South Fork Salmon River corridor on the Payette NF with a short extension on the SFSR Rd on the Boise NF, located generally east of McCall, Idaho in Valley and Idaho Counties.
Project timeline
1
Scoping Start
06/22/2017
2
Comment Period
04/18/2019
3
Objection Period Start
09/30/2020
4
Decision
07/2021 (Estimated)
5
Implementation
07/2021 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Species Habitat Improvements; Special Use Authorizations; Trail Management; Road Improvements/Construction; Travel Management; Watershed Improvements |
| DN2 for 2/16 Actions in South Fork Restoration and Access Management Plan | Decision Signed Date: 07/13/2021 |
| DN1 for 14/16 Actions in South Fork Restoration and Access Management Plan | Decision Signed Date: 07/13/2021 |
| Forests | Payette National Forest |
| Districts | McCall Ranger District; Krassel Ranger District |
| Legal Land Description | Not Applicable |