Treat 1650 acres around town of Cuprum to reduce hazardous fuel loading using a combination of mechanical and hand treatments followed by prescribed fire.
Location
Twenty-two miles northwest of Council, Idaho
Project timeline
1
Scoping Start
02/02/2007
2
Objection Period Start
05/17/2007
3
Decision
07/2010 (Estimated)
4
Implementation
09/2010 (Estimated)
NEPA / regulatory detail
| Special Authority | Hfra Title I: Wildland-Urban Interface |
| Notice and Comment Regulation | 218 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Noxious Weed Treatments; Species Population Enhancements; Watershed Improvements |
| Cuprum Fuels Reduction Project | Decision Signed Date: 07/07/2010 Legal Notice Date: 07/07/2010 |
| Forests | Payette National Forest |
| Districts | Council Ranger District |
| Legal Land Description | T20N R3W Sec. 1-3, 8-11, and 14-22 |