This project is a phased replacement in kind of site furniture at existing recreation sites. Work will focus on replacement of fire pits, pedestal grills, interpretive kiosks, fee tubes, and vault toilets with new and improved versions.
Location
Campgrounds and dispersed sites within the General Forest Areas of the South Fork corridor, Lick Creek corridor, East Fork South Fork corridor and Big Creek areas in Management Areas 12 and 13.
Project timeline
1
Scoping Start
11/28/2018
2
Decision
03/2019 (Estimated)
3
Implementation
04/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Krassel Ranger District Developed & Dispersed Site Improvement Project | Decision Signed Date: 03/29/2019 |
| Forests | Payette National Forest |
| Districts | Krassel Ranger District |
| Legal Land Description | All US Forest Service lands within the following: T17N, R6E; T18N, R6E; T19N, R6E; T19N, R7E; T19N, R8E; T19N, R11E; T20N, R4E; T20N, R5E; T20N, R6E; T20N, R9E; T21N,R9E & T22N, R9E Boise Meridian, Valley and Idaho Counties, Idaho. |