The Forest Service is responding to a request for the issuance of a new special use permit to Eagle Telephone System, Inc. (ETS) for the construction of a new communication facility, access road, and underground powerline.
Location
Located at Lynes Point on the Council Ranger District of the Payette National Forest in Adams County, Idaho.
Project timeline
1
Scoping Start
04/08/2019
2
Decision
06/2019 (Estimated)
3
Implementation
07/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Eagle Telephone System, Inc DBA Snake River PCS Communication Facility | Decision Signed Date: 06/25/2019 |
| Forests | Payette National Forest |
| Districts | Council Ranger District |
| Legal Land Description | Township 20N, Range 3W, section 8 |