Permit construction of a previously authorized 550-ft road and continued use and maintenance of an existing route up Arlise Gulch and authorize reasonable access to a private property.
Location
Approximately 2 miles southwest of Warren, Idaho.
Project timeline
1
Scoping Start
11/22/2021
2
Decision
01/2023 (Estimated)
3
Implementation
02/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Lucky Ben Road Access | Decision Signed Date: 01/18/2023 |
| Forests | Payette National Forest |
| Districts | McCall Ranger District |
| Legal Land Description | T22N, R6E, Sections 9 & 16 |