Decision Memo Completed

Evergreen Pond

Payette National Forest Adams, Idaho New Meadows Ranger District

Install a pipe in an existing pond that will be used to fill a water tank and build a let down fence to around the pond to exclude livestock.

Location

Approximately 10 miles southwest of New Meadows, Idaho.

Project timeline

1
Scoping Start
06/25/2024
2
Decision
10/2024 (Estimated)
3
Implementation
10/2024 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (9), 36 Cfr 220.6(E)(9)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityGrazing Structural Improvements
Evergreen Pond ProjectDecision Signed Date: 10/10/2024
ForestsPayette National Forest
DistrictsNew Meadows Ranger District
Legal Land DescriptionT18N, R1W, NE 1/4 of NW 1/4 of Sec. 24.
Grazing management