The project proposes to repair, rebuild and improve two spring developments within the Indian Mountain C&H Allotment within the Four Corners Fire area.
Location
Located within the Four Corners Fire area and the Indian Mountain C&H Allotment.
Project timeline
1
Scoping Start
11/15/2023
2
Decision
11/2023 (Estimated)
3
Implementation
04/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (11), 36 Cfr 220.6(E)(11) |
| Special Authority | Not Applicable / Other; National Fire Plan - Healthy Forests Initiative Ce |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Structural Improvements |
| Four Corners Fire Spring Reconstruction Project | Decision Signed Date: 11/20/2023 |
| Forests | Payette National Forest |
| Districts | Council Ranger District |
| Legal Land Description | Wolfe Spring/Jeep Spring-T14N R2E Section 24 SWNW (UTM 11N 564863 E 4929621 N). Bull Spring - T14N R2E Section 26 NESW (UTM 11N 565909 E 4931745 N) |