Replace a damaged trail bridge on Pete Creek Trail to restore the stream crossing.
Location
The trail bridge crossing on Lake Creek is located near the NE termini of Pete Creek Trail #144, accessed from the Bear Pete TRHD off NFSR 1901 off NFSR 246, NW of Burgdorf Campground.
Project timeline
1
Scoping Start
04/01/2024
2
Decision
04/2025 (Estimated)
3
Implementation
06/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Trail Management |
| Pete Creek Trail (#144) Bridge Replacement | Decision Signed Date: 04/22/2025 |
| Forests | Payette National Forest |
| Districts | McCall Ranger District |
| Legal Land Description | T 23N, R 4E, section 26 |