Decision Memo Completed

Flanigan water transmission line

Sawtooth National Forest Blaine, Idaho Ketchum Ranger District

Issue new permit for existing spring developement and 421 feet of 1/2 inch poly pipe from National Forest land to Private land for domestic use.

Location

Chocolate Gulch, approx. 5 miles North of Ketchum ID.

Project timeline

1
Scoping Start
03/09/2010
2
Decision
04/2010 (Estimated)
3
Implementation
07/2010 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Flanigan water transmission lineDecision Signed Date: 04/15/2010
ForestsSawtooth National Forest
DistrictsKetchum Ranger District
Legal Land DescriptionSW1/4 SE1/4 Sec.10; lT.5N. R.17E. B.M.
Special use management