Decision Memo Completed

Cave Connector Re-route/Reconstruction

Sawtooth National Forest Cassia, Idaho Minidoka Ranger District

Re-route and reconstruct the steep sections of the Cave Creek Connector Trail to prevent resource damage and to provide a safe trail for public use.

Location

Minidoka Ranger District, Sawtooth National Forest, Cassia Division

Project timeline

1
Scoping Start
03/01/2010
2
Comment Period
03/01/2010
3
Decision
05/2010 (Estimated)
4
Implementation
05/2010 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (1), 36 Cfr 220.6(E)(1)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityTrail Management
Decision Memo Cave Connector Re-route/ReconstructionDecision Signed Date: 05/25/2010 Legal Notice Date: 05/25/2010
ForestsSawtooth National Forest
DistrictsMinidoka Ranger District
Legal Land DescriptionTownship 13 South, Range 21 East Section 25
Recreation management