Decision Memo Cancelled

Grape Creek Restoration Project

Sawtooth National Forest Cassia, Idaho Minidoka Ranger District

Implementation phase to restore 1-2 segments of Grape Creek. This effort will correct several resource issues from past livestock and motorized trail use. Fencing and/or willow planting may be used.

Location

Sawtooth National Forest, Minidoka Ranger District, Albion Division

Project timeline

1
Scoping Start
06/01/2011
2
Decision
06/2012 (Estimated)
3
Implementation
06/2012 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (7), 36 Cfr 220.6(E)(7)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements
ForestsSawtooth National Forest
DistrictsMinidoka Ranger District
Legal Land DescriptionGrape Creek T14S, R24E, Sec. 25
Wildlife, fish, rare plants