Trail bridges will be constructed at two stream crossings on Goose Creek (trails 7912 and 7865) to improve resource conditions and user safety. The lower bridge will be at a new location and will require a reroute of 800 feet of trail 7865.
Location
Sawtooth National Forest UNIT-Minidoka Ranger District, STATE-Idaho, COUNTY-Cassia, DIVISION-Cassia
Project timeline
1
Scoping Start
07/01/2011
2
Comment Period
07/01/2011
3
Decision
08/2011 (Estimated)
4
Implementation
09/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Trail Management |
| DECISION MEMO GOOSE CREEK TRAIL REROUTE AND BRIDGE CONSTRUCTION | Decision Signed Date: 08/04/2011 |
| Forests | Sawtooth National Forest |
| Districts | Minidoka Ranger District |
| Legal Land Description | T 15 S, R 19 E, Sec. 5 and 8 |