Environmental Assessment Cancelled

Frenchman Creek Plan of Operations

Sawtooth National Forest Blaine, Idaho Sawtooth National Recreation Area

Proposed approval of a Plan of Operations for underground mine development on unpatented mining claims in lands open to mineral entry outside of the congressionally designated area of the Sawtooth National Recreation Area.

Location

Unpatented mining claims in the Frenchman Creek drainage.

Project timeline

1
Scoping Start
06/15/2011
2
Comment Period
04/2012 (Estimated)
3
Decision
09/2012 (Estimated)
4
Implementation
11/2012 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityMinerals Or Geology Plans Of Operations
ForestsSawtooth National Forest
DistrictsSawtooth National Recreation Area
Legal Land DescriptionSections 28 & 33, T6N, R14E B.M.
Minerals and geology