The activity will occur on the Sawtooth National Forest in the Lake Creek drainage, approximately three miles north of Ketchum, in the Big Wood River watershed.
Location
Lake Creek drainage
Project timeline
1
Scoping Start
02/27/2014
2
Decision
10/2014 (Estimated)
3
Implementation
11/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Species Habitat Improvements |
| Lake Creek Channel Enhancement | Decision Signed Date: 10/20/2014 |
| Forests | Sawtooth National Forest |
| Districts | Ketchum Ranger District |
| Legal Land Description | R4, Sawtooth National Forest, Ketchum Ranger District, Blaine County, Idaho |