Proposal to construct .2 miles of trail reroute, decommission .3 miles of trail, install one trail bridge, and decommission three trail bridges.
Location
Greenhorn Gulch Trailhead, 12 miles Southwest of Ketchum.
Project timeline
1
Scoping Start
11/06/2023
2
Decision
01/2024 (Estimated)
3
Implementation
07/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (1), 36 Cfr 220.6(E)(1) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Trail Management |
| Greenhorn Gulch Improvement Project | Decision Signed Date: 01/18/2024 |
| Forests | Sawtooth National Forest |
| Districts | Ketchum Ranger District |
| Legal Land Description | T. 3 N.,R. 17 E., Section 15 |