Develop Allotment Management Plan for the Neilsen (Morrison) Allotment that will be incorporated into the term grazing permit and used to guide management of grazing operations.
Location
The Neilsen Allotment is bounded on the north by Highway 50, the east by Silver Fork Road, and the west by Plum Creek and Mormon Emigrant Trail.
Project timeline
1
Scoping Start
08/30/2013
2
Comment Period
06/18/2014
3
Objection Period Start
07/01/2015
4
Decision
09/2015 (Estimated)
5
Implementation
04/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Grazing Allotment Management; Grazing Authorizations; Rangeland Vegetation Improvements; Grazing Structural Improvements |
| Neilsen Grazing Allotment Management Plan | Decision Signed Date: 09/09/2015 |
| Forests | Eldorado National Forest |
| Districts | Placerville Ranger District |
| Legal Land Description | Not Applicable |