Amend PG&E's Master Special Use Permit to include the installation, use, and maintenance of a remote weather station at Bald Mountain. The weather station would be mounted on a wooden pole and be solar powered. Project area is smaller than 0.1 acre.
Location
Project location is on Bald Mountain, north of the Bald Mountain Lookout Tower. This location is approximately 7 air miles east of the Georgetown Ranger District office.
Project timeline
1
Scoping Start
12/07/2021
2
Decision
02/2022 (Estimated)
3
Implementation
03/2022 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Amendment to Pacific Gas and Electric (PG&E) Company's Master Special Use Permit | Decision Signed Date: 02/02/2022 |
| Forests | Eldorado National Forest |
| Districts | Georgetown Ranger District |
| Legal Land Description | Township 12N, Range 11E, Section 12, NW 1/4 |