Rock Creek Road, FSR 12N70, was heavily impacted by the Winter storms of 2022 and is currently impassable. The existing culvert will be replaced with a newly designed culvert and the road and slope will be stabilized.
Location
Washout located on Rock Creek Road, FSR 12N70
Project timeline
1
Scoping Start
09/11/2024
2
Decision
09/2024 (Estimated)
3
Implementation
09/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (18), 36 Cfr 220.6(E)(18) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance; Road Improvements/Construction; Watershed Improvements |
| Rock Creek Stream Restoration Project | Decision Signed Date: 09/19/2024 |
| Forests | Eldorado National Forest |
| Districts | Georgetown Ranger District |
| Legal Land Description | Not Applicable |