Renewal to authorize the maintenance, operation, and construction of about 30 miles (270 acres) of existing powerline. No new disturbance proposed. NCRWQCB Waiver exempt.
Location
Starts at T44N., R9W MDM Sec. 2 off County Road 6G002 on Scott River Rd.; ends T18N. R6E., HM, Sec. 8, at KNF & Six Rivers Forest Boundaries just south of Little Grayback Mt on Happy Camp/Oak RD.
Project timeline
1
Scoping Start
08/01/2012
2
Decision
09/2016 (Estimated)
3
Implementation
10/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Forests | Klamath National Forest |
| Districts | Happy Camp Ranger District |
| Legal Land Description | T46N R7W-12W, MDM; T14N R6E-R8E HM. |