To reduce threats to public safety along National Forest Transportation System roads within the Oak Fire perimeter. Water Board Waiver Category A expected.
Location
The project is located within the Indian Creek, Ukonom Creek-Klamath River, Dillon Creek and Clear Creek 5th field watersheds. The project is about two to ten miles Southwest of Happy Camp.
Project timeline
1
Scoping Start
12/05/2017
2
Decision
09/2018 (Estimated)
3
Implementation
09/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (4), 36 Cfr 220.6(D)(4) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Road Maintenance |
| Oak Fire Roadside Hazard Tree Project | Decision Signed Date: 09/21/2018 |
| Forests | Klamath National Forest |
| Districts | Happy Camp Ranger District |
| Legal Land Description | T15N R5E Sections 15-16, 21-25,27 & 36. T15N R6E Sections 1-4, 9-12, 14-16, 21-23, & 26-29.T5N R7E Sections 5-7. T16N R6E Sections 1-2, 11-13, 24-25, & 36. T16N R7E Sections 16-21 & 29-32.Humboldt Mer |