Replacement of approximately 0.75 miles of deteriorating 1" pipe with 1.5" PVC to an existing trough. Implementation will require digging of a 2' deep ditch in a previously disturbed area. Water Board Waiver n/a.
Location
The project is located 2.5 miles east of the town of Tennant, CA.
Project timeline
1
Scoping Start
07/01/2019
2
Decision
06/2020 (Estimated)
3
Implementation
06/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (9), 36 Cfr 220.6(E)(9) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Grazing Structural Improvements |
| Baird Springs Pipeline Repair | Decision Signed Date: 06/17/2020 |
| Forests | Klamath National Forest |
| Districts | Goosenest Ranger District |
| Legal Land Description | Township 43 North, Range 1 East, Sections 9 and 4, Mt. Diablo Meridian. |