Plan of Operations to core drill 10 sites on 3 mining claims. Drill sites: 10'x10' with a sump area 5'x5' at 4'. Holes: 4-6" in diameter, less than 150' deep; filled with concrete slurry at the end of drilling. Waterboard Waiver B.
Location
Project is located NE of Happy Camp, CA. Indian Creek Headwaters 7th field watershed.
Project timeline
1
Scoping Start
05/11/2023
2
Decision
03/2024 (Estimated)
3
Implementation
06/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Arrowhead Core Drilling | Decision Signed Date: 03/27/2024 |
| Forests | Klamath National Forest |
| Districts | Happy Camp Ranger District |
| Legal Land Description | T19N R6E Sec. 35 and 36. T18N R6E Sec. 2 and 3. Humboldt Meridian. |