Stabilize and restore Knickpoint and spill channel below Philbrook Reservoir. Reduce ongoing channel erosion and sedimentation resulting from reservoir operations.
Location
Approximately 3,000 feet of spillchannel from Philbrook Dam to it's downstream confluence with Philbrook Creek.
Project timeline
1
Scoping Start
11/16/2009
2
Comment Period
07/28/2010
3
Decision
09/2010 (Estimated)
4
Implementation
10/2010 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Species Habitat Improvements; Special Use Authorizations; Watershed Improvements |
| DN/FONSI for Philbrook Spillway Channel Stabilization project | Decision Signed Date: 09/09/2010 Legal Notice Date: 09/15/2010 |
| Forests | Lassen National Forest |
| Districts | Almanor Ranger District |
| Legal Land Description | T25N, R4E, Sec 12 & 13, MDM |