Project timeline

1
Scoping Start
08/07/2012
2
Comment Period
08/27/2013
3
Decision
01/2014 (Estimated)
4
Implementation
06/2014 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityRoad Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green); Watershed Improvements
Dragon Project Decision Notice and FONSIDecision Signed Date: 01/24/2014
ForestsLassen National Forest
DistrictsEagle Lake Ranger District