Installation of an emergency backup propane 50kw generator on a new 4 ft.by 10 ft. concrete pad and a 500 gallon propane tank on a new 5ft.by 12 ft. concrete pad.
Location
Keddie Ridge
Project timeline
1
Scoping Start
07/02/2013
2
Comment Period
07/02/2013
3
Decision
08/2013 (Estimated)
4
Implementation
09/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Keddie Ridge Communication Site Generator Installation Project | Decision Signed Date: 08/02/2013 Legal Notice Date: 08/20/2013 |
| Forests | Lassen National Forest |
| Districts | Eagle Lake Ranger District |
| Legal Land Description | T27N, R9E, section 6 |