Four water development projects including well installation, with storage tanks, troughs, and pipeline, are proposed to provide permanent water sources within the Carr and Tucker Allotments. (Perez Pipeline proposal is now included in this analysis).
Location
Project is located southeast of Tulelake; Tucker Well is north and Harvey Jones Well is just east of Harvey Jones Butte and Red Lake Well is just east of Doublehead Mtn.
Project timeline
1
Scoping Start
11/22/2013
2
Comment Period
10/23/2014
3
Objection Period Start
02/26/2015
4
Decision
07/2015 (Estimated)
5
Implementation
07/2015 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Grazing Allotment Management; Species Habitat Improvements; Rangeland Vegetation Improvements; Grazing Structural Improvements |
| Carr-Tucker Allotments Water Development Projects DN/FONSI | Decision Signed Date: 07/10/2015 |
| Forests | Modoc National Forest |
| Districts | Doublehead Ranger District |
| Legal Land Description | T46NR6E, T45NR6E, T45NR7E |