This project is now combined with the Carr-Tucker Allotments Water Development Projects.
Location
Seven miles south of Clear Lake and four miles east of State Highway 139.
Project timeline
1
Scoping Start
03/03/2014
2
Comment Period
11/06/2014
3
Objection Period Start
02/26/2015
4
Decision
07/2015 (Estimated)
5
Implementation
07/2015 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Species Habitat Improvements; Grazing Structural Improvements |
| Carr-Tucker Allotments Water Development Projects DN/FONSI | Decision Signed Date: 07/10/2015 |
| Forests | Modoc National Forest |
| Districts | Doublehead Ranger District |
| Legal Land Description | T45N R7E Section 32 |