Upgrade failing infrastructure, including construction and demolition to replace deficient, unsafe structures with facilities that meet current needs. Replace underground water and wastewater distribution systems.
Location
Site is on the south boundary of the city of Alturas, bordering the east side of Highway 395.
Project timeline
1
Scoping Start
07/07/2016
2
Decision
08/2016 (Estimated)
3
Implementation
08/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (3), 36 Cfr 220.6(D)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Facility Maintenance |
| South Fork Work Site Redevelopment | Decision Signed Date: 08/29/2016 |
| Forests | Modoc National Forest |
| Districts | Devils Garden Ranger District |
| Legal Land Description | T42N R12E, Section 13 |